EHS Support completed a Phase 2 Environment, Health and Safety (EHS) Assessment for our Client to support the lease and use of a haul road alignment within the Port of Bunbury Inner Harbour. The assessment was undertaken to establish baseline soil conditions prior to and during our Client’s use of the road for caustic transport to their refinery, and to determine whether any contamination risks were present for ongoing industrial use.
The investigation included a targeted soil assessment across the 1.16 km haul road corridor, with 23 shallow test pits installed at regular intervals and samples collected from both surface and subsurface layers. This approach enabled EHS Support to evaluate current surface conditions, infer pre-lease baseline conditions below the surface, and compare all analytical results against relevant commercial and industrial land use criteria. The assessment also included robust QA/QC procedures to confirm the reliability and integrity of the dataset.
The results showed that concentrations of total recoverable hydrocarbons (TRH), BTEX, PAHs and metals were below all applicable assessment criteria for commercial and industrial land use. While some metals and naturally alkaline soil conditions were identified, these were consistent with the site’s made-ground history and did not indicate contamination or unacceptable risk. The findings confirmed that the haul road alignment does not pose an unacceptable risk to human health or the environment.
As a result, the site was determined to be suitable for continued and ongoing industrial use, with no further assessment or monitoring required. The assessment also confirmed that our Client’s use of the haul road since October 2024 has not adversely impacted soil conditions, providing confidence in both the baseline environmental condition of the site and the suitability of the road corridor for ongoing operations.